Construction for the Phase 3 & 4 Wastewater Project is anticipated to impact the following areas for the week of November 24th:
- Main focus of work will be at the Rimrock Lodge
- Working on 8” gravity main and the low pressure forcemains. Potential to install grinder pumps in this area in the next few weeks.
- Sewer main/forcemain install near the High School and north of Golf St past the pool (out of roadway, see map)
o (shown in green on attached map)
- Manholes will be staged on edges of residential roads for the duration of this project, they should be placed off the road but inside the City’s right-of-way, please be aware of these.
- It’s Thanksgiving week starting 11.23.25, construction crews will be working only Monday-Wednesday.
*Note construction schedule is subject to change due to weather, unscheduled field conditions, etc. The weekly schedule is an estimated schedule.
- Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays.
Construction will continue Monday- Wednesday from 7 AM to 7 PM, and take off Thursday and Friday due to the holiday.
We hope everyone has a good Thanksgiving Holiday.