Construction update for the week of 1.12.26
· A crew will be moving the 4'' water line and installing the lift station #4 down on Golf by the school
· A crew will install lift station #5 next and then move to Preston and work on lift station #3
· The main line crews will be installing the mainline in the pasture at the end of Elk St
· Clean up at the Rim Rock
· Crews will start rock hammering today on Preston at the East ramp. That section of Preston will be closed until crews are done installing lift station #3
·
*Note construction schedule is subject to change due to weather, unscheduled field conditions, etc. The weekly schedule is an estimated schedule.
Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays.
Construction will continue Monday- Friday from 7 AM to 5:30 PM with potential cleanup Friday.