Construction for the Phase 3 & 4 Wastewater Project is anticipated to impact the following areas for the week of November 17th:
- Paving was completed a little over a week ago
- Gravel shouldering will continue to be completed on the edges of pavement this week (shown in black on the attached map)
- Sewer main/forcemain install on open Land & City property (near Highschool), and north of Golf St (out of roadway)
- (shown in green on attached map)
- Rimrock Lodge sewer main install will be ongoing
- Manholes will be staged on the edges of residential roads for the duration of this project. They should be placed off the road but inside the City’s right-of-way. Please be aware of these.
- For the following week prior to Thanksgiving, construction crews will be working only Monday- Wednesday.
*Note: construction schedule is subject to change due to weather, unscheduled field conditions, etc.
The weekly schedule is an estimated schedule.
Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays.
Construction will continue Monday - Thursday from 7 AM to 7 PM, and clean-up work will be done on
Friday from 7 AM to 12 PM.