Construction update starting 9/28/26:
· There is a mainline crew working in Pine Tree Hollow.
o They will be there for two weeks, then they will move up to Kaniksu.
· The service crew on Clay St will be there for another week and a half.
o They will then move to Church St.
· The service crew on Elk St will move to Pine Tree Hollow.
o They will then move over to Hill St.
· The crew installing grinder pumps will be working on 5th St and Clay St.
· The crew on Aspen Ct will be pressure testing and connecting those pumps.
o Then they will move up to 5th St and Maple.
· The service crew on Woodland will continue there for the next three weeks.
· A crew will be prepping and paving for the next two weeks on Clay St, Elk St, and Maiden Lane.
· Chip sealing will be done on Greenwood and Adams St North on Monday, September 28th.
o Those streets will need to be CLOSED to thru traffic for two weeks to allow the oil to set.
*Note: construction schedule is subject to change due to weather, unscheduled field conditions, etc. The weekly schedule is an estimated schedule.
Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays.
Construction will continue Monday- Thursday from 7:30 AM to 6:00 PM