• Home
  • Wastewater Projects
  • Growth Policy
  • Infrastructure Project
  • City Council Meeting Info
  • CITY COURT PAYMENTS
  • Council meetings Audio
  • City Ordinances
  • City Pool
  • Beautification Days
  • Departments
  • Mayor's Page
  • Public Works
  • Employment
  • Resources
  • Contact Us
  • Downtown Master Plan
  • Community Center
  • Public Library
  • County Housing Assessment
  • More
    • Home
    • Wastewater Projects
    • Growth Policy
    • Infrastructure Project
    • City Council Meeting Info
    • CITY COURT PAYMENTS
    • Council meetings Audio
    • City Ordinances
    • City Pool
    • Beautification Days
    • Departments
    • Mayor's Page
    • Public Works
    • Employment
    • Resources
    • Contact Us
    • Downtown Master Plan
    • Community Center
    • Public Library
    • County Housing Assessment
  • Home
  • Wastewater Projects
  • Growth Policy
  • Infrastructure Project
  • City Council Meeting Info
  • CITY COURT PAYMENTS
  • Council meetings Audio
  • City Ordinances
  • City Pool
  • Beautification Days
  • Departments
  • Mayor's Page
  • Public Works
  • Employment
  • Resources
  • Contact Us
  • Downtown Master Plan
  • Community Center
  • Public Library
  • County Housing Assessment

Phase 3 & 4 Wastewater Project Updates

Construction for the Phase 3 & 4 Wastewater Project is anticipated to impact the following areas for the week of November 17th:

        

  • Paving was completed a little over a week ago            
  • Gravel shouldering will continue to be completed on the edges of pavement this week (shown in black on the attached map)
  • Sewer main/forcemain install on open Land & City property (near Highschool), and north of Golf St (out of roadway)

- (shown in green on attached map)

  • Rimrock Lodge sewer main install will be ongoing
  • Manholes will be staged on the edges of residential roads for the duration of this project. They should be placed off the road but inside the City’s right-of-way. Please be aware of these.
  • For the following week prior to Thanksgiving, construction crews will be working only Monday- Wednesday. 


*Note: construction schedule is subject to change due to weather, unscheduled field conditions, etc. 

The weekly schedule is an estimated schedule.


Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays. 


 Construction will continue Monday - Thursday from 7 AM to 7 PM, and clean-up work will be done on 

Friday from 7 AM to 12 PM.  


Files coming soon.

Downloads


City of Thompson Falls   

Phases 1 & 2 

Funding Announcement

Call Cindy Donnell, USDA RD  1-406-389-3889

For information regarding grant/loan program and if you would qualify.



Thompson Falls Wastewater

Phases 3 & 4

Funding Announcement

The City has worked to secure $390,000 in funding to help pay the SID assessments for low-to-moderate income individuals in the Phase 3 & 4 project. The grant funds are through the State of Montana Community Development Block Grant (CDBG) program. This program provides direct grant assistance to qualifying low-to-moderate residents (residential properties only) that are landowners or renters. 

As the City works to develop the SID assessment for Phases 3 & 4, information on how to apply for the grant funds will be made available. At this time, the City wants to let residents know the funds are available. You will qualify for the program if your income is at or below the income table shown below. 


Household Size - Household Income


1 - $44,800

2 - $51,200

3 - $57,600

4 - $64,000

5 - $69,150

6 - $74,250

7 - $79,400

8 - $84,500



Files coming soon.

Copyright © 2025 City of Thompson Falls - All Rights Reserved.

  • Home
  • Resources
  • Privacy Policy
  • Privacy Policy
  • Terms and Conditions

Powered by

  

Construction update for the week of 11.17.25 

·   Paving was completed a little over a week ago

- Gravel shouldering will continue to be completed on the edges of pavement this week (shown in black on the attached map)

• Sewer main/forcemain install on open Land & City property (near Highschool), and north of Golf St (out of roadway)

- (shown in green on attached map)

• Rimrock Lodge sewer main install will be ongoing

• Manholes will be staged on the edges of residential roads for the duration of this project. They should be placed off the road but inside the City’s right-of-way. Please be aware.

Sewer Project Updates