• Home
  • Announcements
  • Wastewater Projects
  • City Council Meeting Info
  • Beautification Days
  • Comprehensive Plan 2025
  • Infrastructure Project
  • CITY COURT PAYMENTS
  • Council meetings Audio
  • City Ordinances
  • City Pool
  • Departments
  • Mayor's Page
  • Public Works
  • Employment
  • Resources
  • Contact Us
  • Downtown Master Plan
  • Community Center
  • Public Library
  • County Housing Assessment
  • More
    • Home
    • Announcements
    • Wastewater Projects
    • City Council Meeting Info
    • Beautification Days
    • Comprehensive Plan 2025
    • Infrastructure Project
    • CITY COURT PAYMENTS
    • Council meetings Audio
    • City Ordinances
    • City Pool
    • Departments
    • Mayor's Page
    • Public Works
    • Employment
    • Resources
    • Contact Us
    • Downtown Master Plan
    • Community Center
    • Public Library
    • County Housing Assessment
  • Home
  • Announcements
  • Wastewater Projects
  • City Council Meeting Info
  • Beautification Days
  • Comprehensive Plan 2025
  • Infrastructure Project
  • CITY COURT PAYMENTS
  • Council meetings Audio
  • City Ordinances
  • City Pool
  • Departments
  • Mayor's Page
  • Public Works
  • Employment
  • Resources
  • Contact Us
  • Downtown Master Plan
  • Community Center
  • Public Library
  • County Housing Assessment

Phase 3 & 4 Wastewater Project Updates

        

Construction update starting 9/28/26:


· There is a mainline crew working in Pine Tree Hollow.

o They will be there for two weeks, then they will move up to Kaniksu.


· The service crew on Clay St will be there for another week and a half.

o They will then move to Church St.


· The service crew on Elk St will move to Pine Tree Hollow.

o They will then move over to Hill St.


· The crew installing grinder pumps will be working on 5th St and Clay St.


· The crew on Aspen Ct will be pressure testing and connecting those pumps.

o Then they will move up to 5th St and Maple.


· The service crew on Woodland will continue there for the next three weeks.


· A crew will be prepping and paving for the next two weeks on Clay St, Elk St, and Maiden Lane.


· Chip sealing will be done on Greenwood and Adams St North on Monday, September 28th.

o Those streets will need to be CLOSED to thru traffic for two weeks to allow the oil to set.


*Note: construction schedule is subject to change due to weather, unscheduled field conditions, etc. The weekly schedule is an estimated schedule.

Please be careful around these areas and follow all traffic control signs and directions. Please watch for equipment and truck traffic for your safety. If possible, please use alternate routes to avoid delays. 

Construction will continue Monday- Thursday from 7:30 AM to 6:00 PM

Files coming soon.





Files coming soon.

Copyright © 2026 City of Thompson Falls - All Rights Reserved.

  • Home
  • Announcements
  • Resources
  • Privacy Policy
  • Terms and Conditions
  • Privacy Policy

Powered by

Cookie Policy

This website uses cookies. By continuing to use this site, you accept our use of cookies.

DeclineAccept & Close